Focus On

Focus On messages are road improvement updates sent to households in the immediately affected areas but that may be of use to other surrounding neighborhoods.



Lyon Drive Reconstruction Project
Tuesday, September 23, 2008

The City’s contractor, Decker Construction, is scheduled to begin Phase 2 of the pavement removal and replacement on Thursday, September 25, 2008 (Weather Permitting).

This work will require a 10-day closure of the street to all traffic.

The reconstruction work will be from 3910 Lyon Drive to McCoy Road (also included will be Marysue Lane). This work will include removing the old pavement, grading, preparing, compacting the exposed sub grade, and replacing the roadway. While the roadway is being replaced, the road will be closed to all traffic. Only construction, public service and public safety vehicles will have access to the roadway. All vehicles should be removed from your driveway by 7:30 AM on Thursday, September 25, 2008.

While driveway access is unavailable on your section of the street that is being removed, you may park along the crossing street closest to your house. It is important that you get your car(s) out of your driveway or garage before the pavement is removed. Your trash will still be picked up on the day that it is scheduled. If you could please bring your trash to the curb at the street, that would make it easier for Inland Services to collect.

Barring any unforeseen circumstances (Weather Permitting), the first layer of asphalt work should be completed by Saturday, October 4, 2008. Once this first layer of asphalt is installed, you will once again be able to access your driveways with your vehicles.

We realize this will be an inconvenience, and we will do everything possible to minimize the impact. Your patience and understanding while we complete this project is greatly appreciated.

If you have any questions, please contact the City’s Project Representative Sebastian French at 583-5360 or email at sfrench@uaoh.net. Thank You.



Kioka Avenue Waterline Project
Monday, September 15, 2008

The purpose of this Focus On is to inform you that tomorrow, Tuesday, September 16th, 2008, your water service will be disrupted beginning at 3:00 PM. If all work is completed without complications, the water service should be restored to your home by 6:00 PM.

This work is necessary to connect the recently installed waterline on Kioka Avenue to the watermain on Eastcleft Drive.

The time of disruption, during aforementioned hours, was scheduled to provide the least amount of inconvenience to the public as well as provide continued service to Wickliffe Alternative school during its school day. In light of the recent storm and resulting power outages it is possible that if the Upper Arlington schools are closed on Tuesday this disruption to your water service may be moved up to 9:00 A.M. with the water service being restored no later than 2:00 P.M.

The City appreciates your patience during this process.

If you have any questions or concerns, please contact Jeff Barnhart in the City Engineer’s office at 583-5360 or e:mail: jbarnhart@uaoh.net. Thank you.



Lyon Drive Reconstruction Project
Friday, September 12, 2008

The City’s contractor, Decker Construction, has completed the installation of the curb and gutter and drive aprons on both sides of the street from Grace Lane to McCoy Road. The pavement removal and replacement is scheduled to begin on Tuesday, September 16, 2008 (Weather Permitting).

This work will require a 10-day closure of the street to all traffic.

The reconstruction work will be from Grace Lane to 3910 Lyon Drive. This work will include removing the old pavement, grading, preparing, compacting the exposed sub grade, and replacing the roadway. While the roadway is being replaced, the road will be closed to all traffic. Only construction, public service and public safety vehicles will have access to the roadway. All vehicles should be removed from your driveway by 7:30 AM on Tuesday, September 16, 2008.

While driveway access is unavailable on your section of the street that is being removed, you may park along the crossing street closest to your house. It is important that you get your car(s) out of your driveway or garage before the pavement is removed. Your trash will still be picked up on the day that it is scheduled. If you could please bring your trash to the curb at the street, that would make it easier for Inland Services to collect.

Barring any unforeseen circumstances (Weather Permitting), the first layer of asphalt work should be completed by Friday, September 26, 2008. Once this first layer of asphalt is installed, you will once again be able to access your driveways with your vehicles.

We realize this will be an inconvenience, and we will do everything possible to minimize the impact. Your patience and understanding while we complete this project is greatly appreciated.

If you have any questions, please contact the City’s Project Representative Sebastian French at 583-5360 or email at sfrench@uaoh.net. Thank You.



Ramsgate Road Reconstruction Project
Friday, September 5, 2008

This Focus On is to inform you that the Ramsgate Road Reconstruction Project is nearing completion.

The contractor has furnished and installed new topsoil and seed along the new roadway and has fulfilled his contractual obligations for watering the new grass in order to establish healthy stands of grass.

The City encourages each resident to continue to water the newly established grass in order to continue to facilitate its health and growth. With your assistance, the healthy grass that exists today will continue to flourish. Thank you for your patience as we complete this important project.

If you have any questions or need assistance, please contact Jeff Barnhart of the City’s Engineering Division at 583-5369 or by e-mail at jbarnhart@uaoh.net.



Windham Road Reconstruction Project
Thursday, September 4, 2008

As part of the ongoing 2008 Street Reconstruction Program, the City’s contractor, Decker Construction, will be removing and replacing the drive aprons, and excavating for the installation of curb & gutter on the south side of Windham Road from Carriage Hill Lane to and including 1319 Windham Road. This work is scheduled to begin on Tuesday, September 9th, 2008.

While the drive aprons and the installation for curb and gutters are under construction on the south side, access to your driveway will not be available for a period of about ten (10) days, Weather Permitting.

While driveway access is unavailable on your side of the street, you may park on the opposite side of the street during non-working hours (7:30 PM – 7:30 AM) or, on any of the side streets at any time. It is important that you get your vehicle(s) out of your driveway or garage before your curb and drive apron is removed. There will be no on-street parking available Monday thru Saturday (7:30 AM – 7:30 PM) during this reconstruction project.

It is important that if you have any special circumstance, such as regular delivery of medical supplies or if you or a member of your family are handicapped and cannot walk to and from the remote parking, please contact the City Engineering Division.

Additional notices such as this will be distributed to you as more details become available. We apologize for any inconvenience. Your patience and understanding while we complete this project are greatly appreciated.

In the meantime, if you have any questions, please contact the City’s Project Representative, Paul Selegue at 583-5360 or email at pselegue@uaoh.net.



Henderson Road Corridor Study

The purpose of this notice is to invite you to a public meeting scheduled for Thursday, September 25th, 2008 at 7:00 PM, relative to the Henderson Road Corridor Study. The meeting will be held at the First Alliance Church at the corner of Sawmill Road and Henderson Road, 3750 West Henderson Road.

The section of Henderson Road under study runs from just east of Riverside Drive to just west of Sawmill Road.

At this meeting, the City will discuss the potential improvements created by the engineering personnel from Burgess & Niple, with assistance from City staff, as well as the input that was received at the previous public meeting. Input from the public is an important component of this meeting, and your continued participation is critical to the progress of this study.

If you have any questions or concerns, please contact Jeff Barnhart, Engineering Technician for the City of Upper Arlington at 614-583-5360 or jbarnhart@uaoh.net.



Windham Road Reconstruction Project
Friday, August 15, 2008

As part of the on-going 2008 Street Reconstruction Program, the City’s contractor, Decker Construction, will be removing and replacing the drive aprons, and excavating for the installation of curb & gutter on the north side of Windham Road from Kenny Road to 1314 Windham Road. This work is scheduled to begin on Tuesday, August 19th, 2008.

While the drive aprons and the installation for curb and gutters are under construction on the north side, access to your driveway will not be available for a period of about ten (10) days, Weather Permitting.

While driveway access is unavailable on your side of the street, you may park on the opposite side of the street during non-working hours (7:30 PM – 7:30 AM) or, on any of the side streets at any time. It is important that you get your vehicle(s) out of your driveway or garage before your curb and drive apron is removed. There will be no on-street parking available Monday thru Saturday (7:30 AM – 7:30 PM) during this reconstruction project.

It is important that if you have any special circumstance, such as regular delivery of medical supplies or if you or a member of your family are handicapped and cannot walk to and from the remote parking, please contact the City Engineering Division.

Additional notices such as this will be distributed to you as more details become available. We apologize for any inconvenience. Your patience and understanding while we complete this project are greatly appreciated.

In the meantime, if you have any questions, please contact the City’s Project representative, Sebastian French at 583-5360 or email at sfrench@uaoh.net. Thank you.



Collingswood Road Reconstruction Project
Friday, August 15, 2008

This notice is to inform you about the upcoming reconstruction work on Collingswood Road (from Coventry Road to Northwest Boulevard) that is scheduled to take place in the near future.

The major portions of the work include:

1. New Waterline & Storm Sewer
2. Asphalt Pavement Removal & Replacement
3. Curb & Gutter Removal & Replacement
4. Driveway Approach Removal & Replacement

We would like to hear the opinion of the residents along Collingswood Road regarding the possible installation and placement of a new sidewalk. The approximate cost for sidewalk is $50.00 per running foot. It is the City’s policy that first-time sidewalk installation be paid for by the residents whose property abuts the street. This policy is supported by the fact that first-time sidewalk on other City streets was indirectly paid for by the property owners as part of the original purchase of the property. The developer who built the sidewalk recouped his cost through the sale of the lots to the original homeowners. The proposed sidewalk would be 5 foot wide with a 5 foot tree lawn.

Also, please notify us if you have any dog fences or sprinkler systems that are located behind the curb so that we can try to avoid damaging them during construction.

If you have any questions or are interested in representing your street by conducting an informal petition for new sidewalk or, if you wish to learn more about the process, please contact the City’s Engineering Division at 583-5360 on or before September 15, 2008. Otherwise, the design for the project will proceed without the installation of new sidewalk.



Lyon Drive Reconstruction Project
Wednesday, August 6, 2008

As part of the on-going 2008 Street Reconstruction Program, the City’s contractor, Decker Construction, will be removing and replacing the drive aprons, and excavating for the installation of new curb & gutter on the east side of Lyon Drive from 3910 Lyon Drive to McCoy Road. This work is scheduled to begin on Friday, August 8, 2008.

While the drive aprons and the installation for curb and gutters are under construction on the east side, access to your driveway will not be available for a period of about ten (10) days, Weather Permitting.

While driveway access is unavailable on your side of the street, you may park on the opposite side of the street during non-working hours (7:30 PM – 7:30 AM) or, on any of the side streets at any time. It is important that you get your vehicle(s) out of your driveway or garage before your curb and drive apron is removed. There will be no on-street parking available Monday thru Saturday (7:30 AM – 7:30 PM) during this reconstruction project.

It is important that if you have any special circumstance, such as regular delivery of medical supplies or if you or a member of your family are handicapped and cannot walk to and from the remote parking, please contact the City Engineering Division.

Additional notices such as this will be distributed to you as more details become available. We apologize for any inconvenience. Your patience and understanding while we complete this project are greatly appreciated.

In the meantime, if you have any questions, please contact the City’s Project Representative, Sebastian French at 583-5360 or email at sfrench@uaoh.net. Thank you.



Lyon Drive Reconstruction Project
Tuesday, July 29, 2008

As part of the on-going 2008 Street Reconstruction Program, the City’s contractor, Decker Construction, will be removing and replacing the drive aprons, and excavating for the installation of new curb & gutter on the east side of Lyon Drive from Grace Lane to 3910 Lyon Drive. This work is scheduled to begin on Wednesday, July 30th, 2008.

While the drive aprons and the installation for curb and gutters are under construction on the east side, access to your driveway will not be available for a period of about ten (10) days, Weather Permitting.

While driveway access is unavailable on your side of the street, you may park on the opposite side of the street during non-working hours (7:30 PM – 7:30 AM) or, on any of the side streets at any time. It is important that you get your vehicle(s) out of your driveway or garage before your curb and drive apron is removed. There will be no on-street parking available Monday thru Saturday (7:30 AM – 7:30 PM) during this reconstruction project.

It is important that if you have any special circumstance, such as regular delivery of medical supplies or if you or a member of your family are handicapped and cannot walk to and from the remote parking, please contact the City Engineering Division.

Additional notices such as this will be distributed to you as more details become available. We apologize for any inconvenience. Your patience and understanding while we complete this project are greatly appreciated.

In the meantime, if you have any questions, please contact the City’s Project Representative, Sebastian French at 583-5360 or email at sfrench@uaoh.net. Thank you



Lyon Drive Reconstruction Project
Wednesday, July 23, 2008

As part of the on-going 2008 Street Reconstruction Program, the City’s contractor, Decker Construction, will be removing and replacing the drive aprons, and excavating for the installation of curb & gutter on the west side of Lyon Drive from Marysue Lane to McCoy Road. This work is scheduled to begin on Monday, July 28th, 2008.

While the drive aprons and the installation for curb and gutters are under construction on the west side, access to your driveway will not be available for a period of about ten (10) days, Weather Permitting.

While driveway access is unavailable on your side of the street, you may park on the opposite side of the street during non-working hours (7:30 PM – 7:30 AM) or, on any of the side streets at any time. It is important that you get your vehicle(s) out of your driveway or garage before your curb and drive apron is removed. There will be no on-street parking available Monday thru Saturday (7:30 AM – 7:30 PM) during this reconstruction project.

It is important that if you have any special circumstance, such as regular delivery of medical supplies or if you or a member of your family are handicapped and cannot walk to and from the remote parking, please contact the City Engineering Division.

Additional notices such as this will be distributed to you as more details become available. We apologize for any inconvenience. Your patience and understanding while we complete this project are greatly appreciated.

In the meantime, if you have any questions, please contact the City’s Project Representative, Sebastian French at 583-5360 or email at sfrench@uaoh.net.



Lyon Drive Improvements Project
Tuesday, July 15, 2008

The next stage of the project is the installation of the curb and gutter on the west side of Lyon Drive between Hartsook Lane and Marysue Lane.

The contractor will begin excavating for the curb and gutter on the west side starting on Thursday morning, July 17th, 2008. This means that all residents on the west side of Lyon Drive, from Hartsook Lane to Marysue Lane, will need to have their vehicles out of their driveways by 7:30 AM Thursday morning.

There will be no parking permitted on Lyon Drive during working hours (7:30 AM to 7:00 PM on Monday thru Saturday.)

Weather permitting, the installation of the curb and gutter and driveways will take no more than ten (10) days.

As always, you can contact Sebastian French at 583-5360 with any questions or concerns about this project. Thank you for your patience.



Lyon Drive Improvements Project
Monday July 14, 2008

The next stage of the project is the installation of the curb and gutter on the west side of Lyon Drive between Grace Lane and Hartsook Lane.

The contractor will begin excavating for the curb and gutter on the west side starting on Tuesday morning, July 15th, 2008. This means that all residents on the west side of Lyon Drive, from Grace Lane to Hartsook Lane, will need to have their vehicles out of their driveways by 7:30 AM tomorrow morning.

There will be no parking permitted on Lyon Drive during working hours (7:30 AM to 7:00 PM on Monday thru Saturday.)

Weather permitting, the installation of the curb and gutter and driveways will take no more than ten (10) days.

As always, you can contact Sebastian French at 583-5360 with any questions or concerns about this project. Thank you for your patience.



Ramsgate Road Reconstruction Project
Thursday, July 3, 2008

The Ramsgate Road next stage of the project is the paving of the roadway on Ramsgate Road from Fishinger Road to Swansea Road

The contractor will begin work on the pavement on Monday, July 7th, 2008. All residents on Ramsgate Road, between Fishinger Road and Swansea Road, will need to have their vehicle(s) out of their driveway by 7:30 AM on Monday.

During this phase, Ramsgate Road will be completely closed to all traffic during the working hours of 7:30 AM to 7:00 PM. Weather permitting, the paving of the roadway will take two (2) days. This work will include the final course of asphalt and the asphalt driveway pavement. Residents will be able to access their driveway after 7:00 PM each day.

We realize this work will be an inconvenience in your everyday lives. We will do everything possible to minimize the impact. Your patience is greatly appreciated.

If you have any questions or need assistance, please contact Jeff Barnhart of the City’s Engineering Division at 583-5369.



Kioka Avenue
Waterline Project
Friday, June 6, 2008

This notice is to inform you that the contractor, John Eramo & Sons, Inc., will begin the installation of the 12-inch waterline on Kioka Avenue this Monday, June 9, 2008.

The 12-inch waterline will be installed from Zollinger Road to Fishinger Road, with the installation of new fire hydrants and new house services. This operation will result in the temporary closure of the area of the roadway in which the contractor is working. Traffic control will be in place to notify you of the road closures. The work will start at the Zollinger Road intersection.

During the actual waterline installation, each block of Kioka Avenue will be closed to thru traffic. When work is going on in your particular block, please access your residence from the nearest cross street. For the duration of this project, no parking is allowed on Kioka Avenue during the work hours (Monday through Saturday, 7:00 AM to 7:00 PM).

We realize this work will be an inconvenience. We will do everything possible to minimize the impact. Your patience is greatly appreciated.

If you have any questions or need assistance, please contact Sebastian French or Paul Selegue of the City’s Engineering Division at 583-5360.



Lyon Drive
Reconstruction Project
Thursday, May 29, 2008

The City recently met with representatives from Decker Construction who will be performing the Lyon Drive Reconstruction Project. The contractor will begin the first phase of construction on Monday, June 2, 2008.

The first phase of construction will be the installation of the storm sewer piping on Lyon Drive from 200 feet south of McCoy Road to approximately 30 feet north of the box culvert. This operation will result in the temporary closure of the area of the roadway in which the contractor is working and traffic control signs will be in place.

Until further notice, please do not park on Lyon Drive. As construction progresses, you will receive additional Focus On letters informing you of current construction activities.

All driveways will be accessible, except for short periods, on Lyon Drive until late in June when the actual roadway reconstruction begins. We will notify you when we get closer to the start of the roadway work with specific dates and directions for parking.

We realize this work will be an inconvenience, and we will do everything possible to minimize the impact. Your patience is greatly appreciated.

If you have any questions, please contact the City’s Project Representative, Sebastian French at 583-5360 or by e:mail at sfrench@uaoh.net



Ramsgate Road
Waterline and Reconstruction Project
Wednesday, May 14, 2008

The City has met with representatives from the general contractor, John Eramo & Sons, Inc. The contractor has submitted a project schedule and is eager to get the project underway.

The first phase of the project will begin on Monday, May 19th, 2008. This phase consists of the installation of an 8 inch waterline from Swansea Road to Fishinger Road. This operation will result in the temporary closure of the area of the roadway in which the contractor is working. Traffic control will be in place to notify you of the road closures. Work will start at the north end of Swansea Road.

During the actual waterline installation, each block of Ramsgate Road will be closed to thru traffic. When work is going on in your particular block, please access your residence from the nearest cross street. For the duration of this project, no parking is allowed on Swansea Road during work hours (Monday through Saturday, 7:00 AM to 7:00 PM).

We realize this work will be an inconvenience. We will do everything possible to minimize the impact. Your patience is greatly appreciated.

If you have any questions or need assistance, please contact Sebastian French or Paul Selegue of the City’s Engineering Division at 583-5360.