Columbia Gas has several main pipeline replacement projects scheduled for our community in 2018, with three such projects scheduled to begin in January. These projects will consist of the replacement of existing steel pipelines with new plastic lines. For many households on the affected streets, it will involve running new service lines up to homes and the relocation of interior gas meters to the outside.

Details of the projects are as follows: 

  • Welsford Road and Northam Road:
    • Start Date: tbd
    • Project affects sections of Andover, Welsford, Brandon and Northam roads, and Northwest Blvd
  • Tewksbury Road:
    • Began in January, with a mid-Spring completion goal
    • Project affects sections of Tewksbury, Yorkshire and Tremont roads
  • Guilford Road and Beaumont Road:
    • Began in January, with a completion goal of early summer
    • Project affects sections of Harford, Guilford, Grenoble, Barrington, Waltham and North Star roads, and Northwest Boulevard

At each stage in the process Columbia Gas representatives will contact affected residents in advance – to locate any sprinkler systems or invisible fences before work begins, to determine the best location for the new meter, and in advance of making the service transfer. Please watch for a letter detailing the project and inviting you to the community meeting. Once the project begins, be on the lookout for door hanger notices and other communications with updates that directly affect your home.