City of Upper Arlington, Ohio

2017 Street Reconstruction Program

Updated October 31, 2017

Reed Road Reconstruction Project
Detail: Full Reconstruction from Lane Road to Henderson Road
Timeline: Began September 18
Project Manager: Chad Ritzler, 614-583-5360,

October 31 Update: Work has begun on the east side of Reed Road. Access will be restricted to southbound traffic only through mid November (weather permitting), with a delay on McCoy/Kenny/Henderson for northbound traffic (see the October 26 Focus On below)

Overall Cost:
Approximately $3.8 million (approximately three times the expenditure from past years)
Timeline: tba
Project Manager: Sebastian French, 614-583-5360  |
Project Details: These projects are comprised of complete road reconstruction, new curb and gutter, diriveway apron replacement and storm sewer repairs on sections of the following streets:

  • Avalon Road (Zollinger Road to Kenyon Road) - work began May 11
  • Edgemont Road N (Wyandotte Road to Northwest Boulevard) - work began July 17
  • Harlton Court (Vassar Place to cul de sac) - work began June 22
  • Kenyon Road (Avalon Road to Wickliffe Road) - work began May 11
  • Langham Road (Redding Road to Somerford Road) - work began May 11
  • Mackenzie Drive (Nugent Drive to Meekison Drive) - work begins September 11
  • Melford Road (Inchcliffe Road to Zollinger Road) - work began June 21
  • Middlesex Road (Woodbridge Road to Mountview Road) - work began September 5
  • Milden Road (Redding Road to Tremont Road) – work began May 18
  • Pemberton Drive (Tremont Road to Fishinger Road) – work began June 20
  • Randmore Road (Ardwick Road to Mumford Road) - work begins September 8
  • Ridgecliff Road (Redding Road to Sciotangy, and Colchester Road to Tremont Road) - work began June 5
  • Springhill Drive (Mountview Road to Redding Road) - work begins September 5
  • South Mallway (Arlington Avenue to Waltham Road) - work began July 25
  • Tremont Road (North Star Road to Coventry Road) - work began July 10
  • Waltham Road (Arlington Avenue to Bedford Road) - work began July 25
  • Wilshire Drive (Andover Road to Welsford Road) - work began June 22
  • Wyandotte Road (Tremont Road to corporate line, and Stanford Road to Edgemont Road N)

Please see the Focus On Updates below for details of each project.

Associated Documents

Date of Record: 2017-06-13